Construction & infrastructure · 7 min read
Two PEB quotations for the same shed can differ widely because they cover different things. Use this checklist to compare like with like and catch problems early.
To compare pre-engineered building quotations properly, put them side by side against one written brief and check what each includes: the design, the steel and its coating, the roof and wall sheeting, accessories, transport, erection, foundation coordination and the exclusions. The most common buying mistake is choosing on headline price without noticing that the quotations cover different scope. A low quotation that leaves out erection, insulation or the foundation interface may end up costing more than a higher, complete one.
A pre-engineered building, or PEB, is a steel building made in a factory to your order and assembled on site. Because the supplier designs and manufactures the main structure, your quotation is effectively your specification, so it deserves careful reading before you sign.
Quotations are comparable only if suppliers answer the same question. Prepare a single brief covering the building dimensions, clear height, intended use, equipment and loads, openings, roof and wall finishes, insulation, ventilation, expansion plans and the site location.
Ask suppliers to quote against it and to list their assumptions in writing. If a supplier suggests a change to your brief, ask for a separate priced option rather than a silent substitution. That way you can see what you are choosing between.
Give every supplier the same deadline and the same opportunity to ask questions, and keep your answers in writing, so that nobody is working on different information.
A complete quotation names what you are buying in enough detail to be checked on delivery. Look for these items.
Where an item is missing, ask whether it is excluded or merely not mentioned. Silence usually becomes your cost later.
These errors appear again and again, and each is avoidable.
Price differences often reflect differences in scope, steel thickness, coating quality or accessories. Compare the lists line by line. A quotation that looks much lower than the rest deserves a careful question about what is missing or reduced.
The supplier designs the steel and gives the loads to the foundation, while a civil contractor builds the foundation and the anchor bolts must match the steel exactly. When nobody owns this interface, bolts are misplaced and delays follow. Settle in writing who designs, who supplies, who places and who checks.
Because steel is made to size, late changes to openings, equipment loads or layout cause rework and delay. Fix the brief before approving drawings, and treat any change after approval as a priced variation.
Some quotations supply materials only. Others include erection but exclude cranes, power or site access. Confirm who erects, who provides lifting equipment and who is responsible for safety and any damage.
Coastal air, chemical exposure, heavy rain and heat all affect coatings, fasteners and sheeting. Tell the supplier about the conditions, and ask what maintenance the building will need. A cheap coating on a harsh site may cost far more over time.
A warranty that does not say what it covers, for how long and under what conditions is of little use. Ask for the terms in writing, including what the owner must do, such as regular maintenance, to keep the warranty valid.
A good quotation from a weak supplier is still a risk. Ask to see finished buildings and, if possible, speak with the owners. Visit the factory if you can, and look at how members are made, checked and stored.
Ask how the design is prepared and checked, and who is accountable for it. Ask about the supplier's capacity to deliver on schedule, and about how it handles problems on site. Find out how it supports the building after handover.
Confirm the supplier's registrations and tax compliance where the law requires them, and ask about insurance for transit and erection. Requirements differ by project and location, so confirm what applies.
| Often missing item | Why it matters |
|---|---|
| Erection and lifting equipment | Without it, you may face a separate contract and a separate cost |
| Insulation, skylights, ventilators | These change comfort, cost and appearance, and are often priced as extras |
| Anchor bolts and foundation interface | Errors here halt erection and cause rework |
| Gutters, downpipes, flashings | Needed for a weathertight building and often left to the owner |
| Transport and unloading | Distance and site access can add noticeably to the total |
| Warranty details | Unclear terms leave you uncovered when something goes wrong |
Do not pay far ahead of progress
Be careful with large advances before drawings are approved or materials are delivered. Link payments to documented milestones such as approved drawings, dispatch and erection progress, and take advice on the terms before signing. Do not rely on verbal assurances about delivery dates.
Two quotations, one shed
An owner received two quotations for the same warehouse. The lower one excluded erection, insulation and gutters, used lighter sheeting and left the anchor bolts to the owner. After adding the missing items and checking the specification, the owner found the two close in real terms, and chose the supplier with the clearer scope and a verified record. This is a hypothetical illustration.
Prepare one brief, send it to a few suppliers, and compare the replies against the checklist. Ask your own engineer to review the final drawings before approving them. If you want a second pair of eyes on a quotation, Lalsar Infra can review it with you.
Key terms
Questions
A few is usually enough, provided they answer the same brief. More quotations only help if you have the time to compare them properly. Quality of comparison matters more than quantity of bids.
Because they often cover different things: steel thickness, coatings, sheeting, insulation, accessories, erection and transport. Differences in assumptions also change price. Put the quotations in a table and compare each line to see what really differs.
Either can work. What matters is clear responsibility for safety, equipment, quality and damage. Some owners prefer the supplier, who knows the system, while others prefer a separate crew. Confirm the arrangement in writing before signing.
It should state what is covered, such as structure, coating or sheeting, for how long, and what conditions apply, including maintenance. Ask for the full text and read the exclusions. Warranty terms differ between suppliers.
Yes. Ask suppliers to clarify scope, justify specifications and adjust terms. Negotiate on a like-for-like basis, so a lower price is not achieved by quietly reducing the scope. Record agreed changes in the final contract.