Short answer
Start with a complete equipment list, record each item's rating from its nameplate or supplier data, add the figures in a consistent unit, and then have a qualified electrical designer confirm the total. The supply authority will ask for this connected load in its application, so a careful, documented list avoids corrections, delays and an undersized connection.
Connected load is the sum of the ratings of everything you intend to connect. It is a paperwork figure for the application, separate from the designer's estimate of demand actually drawn together, but the two are closely related and the same equipment list feeds both.
Work room by room or machine by machine rather than from memory. For each item note its description, quantity, rating and whether it is a motor, heating element, lighting or electronic load. Include the unglamorous items that are easy to forget: water pumps, ventilation, air conditioning, lifts, office equipment, outdoor lighting and any planned future machines.
Keep ratings in one unit throughout. Mixing different units is a common cause of wrong totals, and an electrical designer will usually convert and check them anyway.
Things people overlook:
Ask for the current format
Supply authorities publish their own application forms, categories and declarations, and these change. Ask the authority or your designer for the version currently in use, and do not rely on a figure remembered from an old connection.
Have the designer review the list before you file it. If the declared load is far from what you later install, the authority may require amendments, and you may face revised charges or a changed connection category. Retain a copy of the list you submitted with the rest of your project records.
Last reviewed
This answer is general information, not advice on your particular case. Terms, eligibility, and requirements change, so check the current position with the relevant institution or authority.