Short answer
The answer depends on the contract. Usually the waterproofing layer is a civil or specialist waterproofing scope, while the plumber places pipes and drain bodies and the junctions between them must be sealed by whoever the contract names. Because this interface is where leaks often start, the owner should have it written down, with one party accountable for the finished, tested result.
A bathroom floor depends on several trades working in sequence. Plumbers fix the pipes and floor drains, civil or finishing teams form the slab and slope, a waterproofing applicator lays the membrane, and tilers finish the surface. Each trade can do its own part correctly and the bathroom can still leak, because the weak points sit at the joints between them.
The usual trouble spots are where pipes pass through the slab, around the edges of floor drains, and at the junction of floor and wall. If the plumber installs a pipe after the membrane is laid, or the applicator stops short of the drain body, water finds the gap.
So who is responsible? There is no single universal answer. In practice it follows the contract and the sequence of work:
Gaps in scope become disputes
If the plumbing quotation says nothing about sealing around pipes and the civil quotation says nothing about drain edges, each party can say it was not theirs. Ask both to confirm in writing who covers the interface.
Ask for a water retention test of the finished floor, carried out and recorded before tiling, and again where the contract requires it. The method and duration follow the specification and applicable standards, set by the designer. Also check what warranty covers waterproofing and who honours it.
Last reviewed
This answer is general information, not advice on your particular case. Terms, eligibility, and requirements change, so check the current position with the relevant institution or authority.