Short answer
Fix the materials in writing before work starts, approve physical samples, and keep those samples on site. Then check deliveries as they arrive against brand, grade and batch details, ask for purchase bills for key items, and inspect work stage by stage. Substitution is much harder when the specification is precise and checks happen before materials are fixed in place.
Disputes about materials usually begin with loose wording. "Good quality plywood" or "branded paint" leaves room for interpretation. A specification that names the product, grade, finish and thickness class leaves much less.
Start by attaching a finish and material schedule to the contract. Each line should say what product, from which maker, in which grade, and where it is used. If equivalents are allowed, say who approves them and that the approval will be in writing.
Samples are the second layer. Collect and sign off physical samples of laminates, tiles, hardware, paint shades and boards. Keep the approved set, labelled and dated, in the site office or with you.
Then control the flow of materials:
Keep inspections before the cover-up
Once a ceiling is closed or a surface is laminated, checking what lies under it is costly. Inspect at the open stage, and take dated photographs.
Link a part of each payment to material verification and stage completion. This creates a natural moment to check before money moves. Remain courteous but consistent, since contractors generally respond well to clear systems.