Project Finance · Question
Short answer
Often yes, but not always. Many lenders ask that the promoter's contribution is spent first, or alongside the first tranche, so the lender is never funded ahead of the owner. Others allow a pro-rata mix in the sanctioned ratio. The order is fixed in the sanction terms, so settle it before you commit any cash.
Think of the loan as a set of gates rather than a single cheque. The sanction letter, together with the means of finance in your plan, sets out how the total cost is paid for: your contribution, the lender's term loan, and any other sources. The tranche schedule then says which source pays at which point.
Many lenders ask that the promoter's contribution goes in before or alongside the loan, so the lender is never exposed ahead of the owner. Others allow a pro-rata mix, where each payment is funded from both sources in the sanctioned ratio. Which model applies is a negotiation point worth settling at sanction, because it affects how much cash you must arrange up front.
What typically triggers a tranche:
| Stage of project | What a lender commonly looks for |
|---|---|
| Early works and land development | Promoter money deployed, title and permissions in place |
| Structure and civil works | Verified progress and paid bills |
| Plant and machinery | Orders placed, advances paid, supplier documents |
| Trial and start of operations | Installation complete, required licences obtained |
Keep a buffer. Costs often rise during construction, and a lender will not automatically fund an overrun, so decide early how you will meet one. If an overrun is likely, speak to the lender before spending, since a pre-agreed arrangement is easier than a request after the fact.
Last reviewed
This answer is general information, not advice on your particular case. Terms, eligibility, and requirements change, so check the current position with the relevant institution or authority.