Demolition & Site Clearance · Question
Short answer
Build one comparison sheet with every activity listed in rows and each contractor in a column, then mark what is included, excluded or unclear. Ask each bidder to price the missing items or confirm them as nil. Only after the scopes match should you compare totals. The lowest figure often belongs to the quote that quietly leaves out the costly parts.
Quotations differ because contractors imagine different jobs. One prices the structure only, another includes carting debris, a third assumes you will clear the foundation. Comparing the bottom lines is like comparing a car with and without wheels.
Start by writing a neutral scope list from your own side: what must come down, to what level, what services will be disconnected and by whom, what happens to debris and salvage, how the ground is left, and what permissions are needed. Then test each quotation against it.
Questions that expose the gaps:
Beware of vague lump sums
A single figure with no breakdown makes later additions hard to challenge. Ask for an item-wise split, even if the contract stays lump sum, so variations have a reference point.
Also compare how each bidder approached the job. A contractor who visited the site, asked about neighbours and described a sequence is pricing a real plan. One who sent a figure by message after a glance is pricing a guess. Check licences, insurance and references on the same sheet.
Finally, record what you agreed in the work order, not in conversation.
Last reviewed
This answer is general information, not advice on your particular case. Terms, eligibility, and requirements change, so check the current position with the relevant institution or authority.