Civil and Precast Construction · Question
Short answer
A bill of quantities, often called a BOQ, is an itemised list of the work in a project, showing each item's description, unit, quantity and price. It turns drawings and specifications into a priced schedule. It matters because it lets you compare bids on equal terms, measure work done for payment and price changes later without arguing from scratch.
Imagine a contractor quoting for a warehouse foundation. Without a schedule, the quote might say one amount for foundation work. With a BOQ, the work is broken into excavation, concrete, reinforcement steel, formwork, backfilling and similar items, each with a quantity taken from the drawings and a price per unit.
The quantities usually come from a quantity surveyor or the design team measuring the drawings, though some contractors prepare their own. When several contractors price the same schedule, differences show up in rates, not in what each assumed was included.
| Column | What to look for |
|---|---|
| Description | Clear wording tied to the specification |
| Unit | Cubic, square or running measure suited to the item |
| Quantity | Figure derived from drawings, not a guess |
| Rate and amount | Price per unit and the total for that line |
An owner reading a BOQ should look for items that are missing, lumped vaguely or marked provisional. Provisional sums hold a place for work whose scope is not yet known, so they are the likeliest source of later cost increases. Check that the drawings and specifications referred to in the BOQ are the same version you intend to build from.
Keep it alive after signing
Use the same BOQ format for running bills and for pricing any added work, so everyone measures against one reference.
A BOQ is only as good as the drawings behind it. If design is incomplete, quantities are estimates, and the final cost is decided by measurement after the work is done. In an item rate contract, that remeasurement drives payment; in a lump sum contract, the BOQ mainly serves as a pricing and variation reference.